Rainbow Lake, BC
![](https://lcreclaim.com/wp-content/uploads/2020/02/Rainbow-Lake-Project.jpg 891w, https://lcreclaim.com/wp-content/uploads/2020/02/Rainbow-Lake-Project-300x139.jpg 300w, https://lcreclaim.com/wp-content/uploads/2020/02/Rainbow-Lake-Project-768x356.jpg 768w)
Highlight for project
Date: May 20, 2009
Location: Rainbow Lake, BC
Service Type: In-Situ
Prior to treatment, there was a thick layer of crude oil on the surface of the water and the surrounding vegetation was dying/killed off. 90 days after treatment with Bio-Reclaim™, vegetation began to return and a clear remediation of the crude oil and bitumen had been completed.